The Culligan distribution and water bottling plant in Inver Grove Heights, MN, was awarded as a negotiated design/build process. An architect was engaged to design the facility, which was to include office space, a clean room for bottling water, a distribution warehouse and a vehicle maintenance area. The construction process was completed in 120 days from excavation to interior finish.
Specifications:
Project Cost:
$2,000,000
Square Footage:
8,000
Construction Type:
concrete block construction
Timeframe:
6 months to complete
General:
clean room for bottling
distribution warehouse
vehicle maintenance area